- Project Time: 2002 - 2004
- Between 2002 and 2004 CBHCC implemented Kikatiti water and health project.
- The Project involved four villages namely Kikatiti, Maroloni, Kitefu and Samaria.
- Implemented activities included laying pipes from the intake to the four villages.
- Construction of two water tanks (one 50,000 gallons and one 20,000 gallons, and rehabilitation of 20,000 gallons tank)
- Construction of domestic points.